Production Losses: How to Find and Reduce Them
Calculate both OEE and TEEP for the plant. Uptime Scheduled Time = 960 minutes/day Run Time = 960 minutes scheduled – (100 minutes unscheduled downtime + 30 minutes changeover) = 830 minutes/ day Uptime = 830 run minutes / 960 scheduled minutes = % Speed Actual Rate = 480 units / (830 run minutes / 60 minutes/hour) = units/hour